Order situation

January – March 2025

Orders received continued to be high during the first quarter 2025 and amounted to SEK 16,574 million (17,889). The level of orders received rose in business areas Construction, Industry and Project Development while it fell in business area Civil Engineering, which had a very high level in the comparable period. Paving contracts increased in business area Industry in both Sweden and Finland. Business area Project Development started production of more tenant-owner apartments/condominiums than in the corresponding quarter last year, which had a positive effect on the level of orders received. There is a large portion of projects for the public sector in orders received for the Group.

Order backlog yet to be produced at the end of the period grew and amounted to SEK 51,955 million (47,808). Of the total order backlog, 47 percent (46) is expected to be produced after 2025 (2024). Swedish operations accounted for 78 percent (81) of the order backlog.

Preliminary agreements

Operations in business areas Construction and Civil Engineering often participate in dialogues with customers at an early stage prior to planned projects, so-called phase 1 contracts. Through these preliminary agreements Peab is contracted to arrive at, together with the customer, an optimal product with the right quality and also deal with risks and uncertainties. As of 2024, we present the potential value of the final construction contracts generated by these preliminary agreements.

At the beginning of 2025 the potential value was around SEK 13 billion. During the period several projects went from phase 1 to phase 2, which means that the projects have been converted into construction contracts and included in Peab’s orders received. At the same time, we see that new projects have flowed into phase 1 while other projects have fallen away. During the quarter most of the new projects are in business area Construction. The value of the construction contracts generated from these phase 1 contracts at the end of March was around SEK 16 billion, and these orders will potentially be received over the next two years.

Orders received

Order backlog

Project size of order backlog, March 31, 2025

Order backlog allocated over time

Sörgården Preschool

Gislaved

We received a number of major construction projects and contracts in the first quarter, including:

The following own housing developments of tenant-owner/condominium apartments were production-started in the first quarter:

We received a number of paving contracts in the first quarter, including: