Order situation
April – June 2022
The level of orders received in the second quarter 2022 amounted to SEK 14,334 million compared to SEK 13,094 million for the same quarter last year.
Orders received were higher in business areas Construction, Civil Engineering and Industry compared to the second quarter 2021. Included in business area Civil Engineering is the commission to rebuild the lock canal in Södertälje for The Swedish Transport Administration for SEK 1.5 billion. Orders received were lower in business area Project Development as a result of fewer production starts of our own housing developments.
January – June 2022
The level of orders received in the first half-year 2022 increased and amounted to SEK 29,709 million compared to SEK 27,540 million for the same period last year.
Orders received in business area Civil Engineering and Industry increased while orders received in business area Project Development contracted. The level of orders received in business area Construction was relatively unchanged compared to the corresponding period in 2021.
Order backlog yet to be produced at the end of the period amounted to SEK 49,899 million compared to SEK 46,684 million at the end of the same period last year. Of the total order backlog, 57 percent (54) is expected to be produced after 2022 (2021). Swedish operations accounted for 76 percent (77) of the order backlog.
Orders received
| MSEK | Apr-Jun 2022 | Apr-Jun 2021 | Jan-Jun 2022 | Jan-Jun 2021 | Jul-Jun 2021/2022 | Jan-Dec 2021 | |
| Mkr | Apr-jun 2022 | Apr-jun 2021 | Jan-jun 2022 | Jan-jun 2021 | Jul-jun 2021/2022 | Jan-dec 2021 | |
| Construction | Bygg | 6,926 | 6,088 | 12,921 | 13,117 | 30,707 | 30,903 |
| Civil Engineering | Anläggning | 4,375 | 3,612 | 9,355 | 8,220 | 15,954 | 14,819 |
| Industry | Industri | 3,614 | 2,999 | 7,449 | 6,301 | 11,716 | 10,568 |
| Project Development | Projektutveckling | 1,530 | 2,496 | 4,025 | 5,003 | 9,003 | 9,981 |
| Eliminations | Elimineringar | -2,111 | -2,101 | -4,041 | -5,101 | -9,363 | -10,423 |
| Group | Koncernen | 14,334 | 13,094 | 29,709 | 27,540 | 58,017 | 55,848 |
Order backlog
| MSEK | Jun 30 2022 | Jun 30 2021 | Dec 31 2021 | |
| Mkr | 30 jun 2022 | 30 jun 2021 | 31 dec 2021 | |
| Construction | Bygg | 28,839 | 26,427 | 30,142 |
| Civil Engineering | Anläggning | 16,408 | 14,689 | 13,955 |
| Industry | Industri | 6,973 | 6,509 | 3,886 |
| Project Development | Projektutveckling | 6,698 | 6,833 | 6,555 |
| Eliminations | Elimineringar | -9,019 | -7,774 | -9,220 |
| Group | Koncernen | 49,899 | 46,684 | 45,318 |
Project size of order backlog, June 30, 2022
Order backlog allocated over time
Post Nord
Södertälje
We received a number of major construction projects and contracts in the second quarter, including:
- Delivery and mounting frames for two new apartment blocks with 160 rental apartments in Upplands Väsby. The customer is Väsbyhem AB. The contract is worth SEK 101 million.
- Construction of a new bridge to the new city borough Varvsstaden in Malmö. The customer is Malmö City and the contract is worth SEK 206 million.
- Construction of the new block Gladan with 85 rental apartments, a parking garage and commercial space in central Gällivare. The customer is LKAB. The contract is worth SEK 349 million.
- Continuing to prepare for the blasting work necessary to make room for a 140 meter long basin hall where waste water is treated through a biological process in Trollhättan. The customer is Trollhättan Energi. The contract is worth SEK 125 million.
- Construction of 46 tenant-owner apartments in Inre Hamnen in Norrköping. The customer is Riksbyggen. The contract is worth SEK 103 million.
- Renovation project of the A Building of the Women’s Hospital at the Helsinki University Hospital (HUS) in Helsinki. The customer is HUS Kiinteistöt Oy. The contract is worth EUR 30 million.
- Construction of 94 tenant-owner apartments in Rosendal in Uppsala Municipality. The customer is OBOS Kärnhem Bostadsproduktion AB. The contract is worth SEK 162 million.
- Construction of a new tech building, new culverts and an energy storage room at Hudiksvall Hospital. The customer is Region Gävleborg. The contract is worth SEK 695 million.
- Construction of three apartment buildings in Järvenpää in Finland. The customer is Avain Rakennuttaja Oy. The contract is worth EUR 14 million.
- Rebuilding E45/Highway 70 through Mora. The customer is the Swedish Transport Administration. The contract is worth SEK 143 million.
- Renovation of Rimnersvallen Stadium to meet standards for parasport, Swedish Championships in track and field and Superettan in soccer and also be completely accessibility adapted for athletes and the public. The customer is Uddevalla Municipality. The contract is worth SEK 211 million.
- Construction of 381 rental apartments on Sorgenfri in Malmö. The customer is Trianon. The contract is worth SEK 430 million.
- Rebuilding the lock canal in Södertälje. The customer is the Swedish Transport Administration and the contract is worth SEK 1.5 billion.
- Extension of Sörbyn Prison south of Umeå. The customer is Specialfastigheter. The contract is worth SEK 364 million.
- Construction of a new office building and test hall in Örnsköldsvik. The customer is BAE Hägglunds AB. The contract is worth SEK 358 million.
- Construction of 138 apartments in the project Trägården stage 2 in Askim in southern Gothenburg. The customer is Stena Fastigheter Göteborg AB. The contract is worth SEK 225 million.
A number of our own housing development projects were production-started in the second quarter, including:
- Vaasan Laivuri comprising 70 apartments. The project is expected to be completed in September 2023.
- Turun Kakolan Torni in Turku comprising 58 apartments. The project is expected to be completed in September 2023.
- Brf Bellevue in Örebro comprising 59 apartments. The project will be certified according to the Swan environmental certification and is expected to be completed in September 2024.
- Brf Blåbär in Umeå comprising 42 apartments. The project will be certified according to the Swan environmental certification and solar panels will be placed on the roofs. It is expected to be completed in October 2024.
- Brf Kajpromenaden in Karlstad comprising 64 apartments. The project will be certified according to the Swan environmental certification and is expected to be completed in June 2025.
- Brf Strandängen 3 in Österåker comprising 39 apartments. The project will be certified according to the Swan environmental certification and is expected to be completed in August 2024.
- Brf Framtiden in Skellefteå comprising 87 apartments. The project will be certified according to the Swan environmental certification and is expected to be completed in January 2025.
- Oulun Sepänportti comprising 45 apartments. The project is expected to be completed in August 2023.
We received a number of federal and municipal paving contracts in the second quarter, including:
- Three-year municipal contract in Katrineholm, Flen and Vingåker worth SEK 30 million. The asphalt volume is in total 30,000 tons.
- One-year municipal contract in Landskrona worth SEK 30 million. The project involves a great deal of groundwork. The asphalt volume is in total 500 tons.
- Two-year federal contract in District Norra Skåne worth SEK 76 million. The asphalt volume is in total 76,000 tons.
- One-year federal contract in southern Finland worth EUR 21.1 million. The asphalt volume is in total 302,000 tons.
- One-year federal contract in northern Savonia worth EUR 6.6 million. The asphalt volume is in total 100,000 tons.
- One-year regional contract in Nordland worth NOK 59 million. The asphalt volume is in total 56,000 tons.
- One-year regional contract in Nærøysund worth NOK 50 million. The asphalt volume is in total 65,000 tons.
- One-year regional contract in Larvik and Sandefjord worth NOK 43 million. The asphalt volume is in total 38,000 tons.
- One-year municipal contract in Porvoo worth EUR 1.6 million. The asphalt volume is in total 21,000 tons.
- One-year municipal contract in Syddjurs Municipality worth DKK 10 million. The asphalt volume is in total 11,000 tons.